During the summer break, PUSD is removing fire-related contaminants in impacted soil areas at 11 campuses and sites following the Eaton Fire. The work is being completed in alignment with and under the oversight of the California Department of Toxic Substances Control (DTSC). PUSD has worked closely with environmental experts, arborists, and DTSC to assess fire-related contaminants impacting soil and trees and determine the appropriate next steps.
The work will take place while students, staff, and community are off campus. Restricted areas have remained closed since last year, and affected areas will be restored with clean soil and replacement trees to support safe, healthy school environments.
We will continue to provide updates as the work progresses.
Messages
-
September 4, 2026 - Message on Longfellow Tree Review | Español
-
August 31, 2026 - Update on Soil Remediation & Trees at Longfellow Elementary | Español
-
July 30, 2026 - PUSD Provides Update on Eaton Fire Soil Remediation, Campus Restoration and Safety | Español
-
July 14, 2026 - Statement and Timeline Documenting PUSD’s Soil Remediation Process and Coordination with Public Agencies | Español
-
July 9, 2026 - Message on Today’s Events at John Muir | Español
-
June 19, 2026 - Board Votes to Continue Soil Remediation and Allow for Tree Retention Alternatives | Español
- June 16, 2026 - Statement on Community Concerns on Safe Soil Cleanup Following The Eaton Fire | Español
- June 15, 2026 - Joint Statement From DTSC and PUSD on Safe Soil Cleanup and Restoration of Campuses Following the Eaton Fire | Español
- May 29, 2026 - Eaton Recovery: Restoring Outdoor Spaces | Español
- Removal and Restoration - Summer 2026
- Frequently Asked Questions - Summer 2026
- Soil Removal - August 2025
- Soil Test Results - May 2025
Removal and Restoration - Summer 2026
DTSC
- August 31, 2026 DTSC Letter re: Longfellow
- Fire-Related Investigation Findings Summary Letter
- Video of DTSC April 16, 2026 Public Meeting Draft Removal Action Workplan
-
DTSC reviewed the District’s Fire-Related Campus Assessment Reports and Removal Action Workplans (RAWs). More information about the DTSC School Cleanup Program is available at: https://dtsc.ca.gov/
evaluating-cleaning-up-school- sites. The reports are located on the DTSC website at https://www.envirostor.dtsc.ca.gov/public/ (search school name).
Final Soil Removal Maps - School and Non-School Sites
- Final Soil Removal Map - Blair May 2026
- Final Soil Removal Map - Cleveland Campus May 2026
- Final Soil Removal Map - Ed Center May 2026
- Final Soil Removal Map - Field May 2026
- Final Soil Removal Map - Franklin May 2026
- Final Soil Removal Map - Jefferson May 2026
- Final Soil Removal Map - Longfellow May 2026
- Final Soil Removal Map - Muir May 2026
- Final Soil Removal Map - Octavia E. Butler May 2026
- Final Soil Removal Map - San Rafael May 2026
- Final Soil Removal Map - Washington May 2026
Tree Removal Maps
- Tree Removal Map & List (Updated)
- Tree Removal Map - Blair
- Tree Removal Map - Ed Center
- Tree Removal Map - Field
- Tree Removal Map - Jefferson
- Tree Removal Map - Longfellow | Longfellow Front Lawn Map 08.31.26
- Tree Removal Map - Muir
- Tree Removal Map - Octavia E. Butler
- Tree Removal Map - San Rafael
- Tree Removal Map - Washington
Soil Cleanup Notices - School and Non-School Sites
- Soil Cleanup Notice - Blair June 2026 | Español
- Soil Cleanup Notice - Cleveland June 2026 | Español
- Soil Cleanup Notice - Education Center June 2026 | Español
- Soil Cleanup Notice - Franklin June 2026 | Español
- Soil Cleanup Notice - Jefferson June 2026 | Español
- Soil Cleanup Notice - John Muir June 2026 | Español
- Soil Cleanup Notice - Longfellow June 2026 | Español
- Soil Cleanup Notice - Octavia E. Butler June 2026 | Español
- Soil Cleanup Notice - San Rafael June 2026 | Español
- Soil Cleanup Notice - Washington June 2026 | Español
Frequently Asked Questions - Summer 2026
- Why is soil being removed at some PUSD campuses?
- What contaminants were found?
- Why is lead a particular concern for children?
- Which campuses and sites are affected?
- Who is overseeing the cleanup?
- Is this work optional?
- Why does this need to happen now?
- Why are trees being removed?
- Is DTSC requiring PUSD to remove trees?
- Is PUSD trying to save trees?
- Why are trees being removed if they are not in areas where students usually play?
- Were protected trees removed at John Muir Early College Magnet on July 1?
- Were native and/or mature trees removed at Jefferson Elementary School?
- What is air knifing, and why didn’t it work at Longfellow Magnet School?
- What happened at San Rafael Elementary School?
- How is PUSD protecting migratory nesting birds?
- What safety measures are in place during soil removal?
- What happens after contaminated soil is removed?
- Will trees be replaced?
- Will wood from removed trees be preserved or repurposed?
- Why not use another method to remediate the soil without removing trees?
- How has PUSD communicated its soil removal plans?
- Where can families and community members find more information?
Why is soil being removed at some PUSD campuses?
Following the Eaton Fire, and related public health guidance, including the Pasadena Public Health Department’s Guidance for Schools and Early Childhood Education Centers to Prevent Lead Exposure, PUSD conducted environmental testing at District campuses and sites.
That testing identified fire-related contaminants, including lead, arsenic, and other substances, in soil at multiple District properties. Areas where impacted soil was identified were closed to protect students, staff, families, and community members.
Eight campuses were cleaned up prior to the start of the 2025-2026 school year. The remaining 11 campuses and sites have significant volumes of fire-related contaminant-impacted soil that must be removed and replaced so campuses can safely reopen for the 2026-2027 school year.
PUSD and the California Department of Toxic Substances Control (DTSC) are aligned in their commitment to oversee safe soil cleanup and restoration. See the DTSC’s February 25, 2026 letter. The District is working carefully and urgently to complete this work before students return.
What contaminants were found?
PUSD’s environmental testing evaluated fire-related contaminants in soil, including heavy metals such as lead, arsenic, cadmium, chromium, copper, nickel, and zinc. Samples were also tested for asbestos fibers. A subset of samples, based on location and sensitive areas, was also analyzed for polycyclic aromatic hydrocarbons (PAHs), and dioxins and furans. Based on the findings of the environmental testing: arsenic, lead, PAHs, and dioxins and furans were detected above regulatory screening values in surficial soil at 19 campuses and properties.
These substances can be associated with fire-damaged structures, ash, debris, and contaminated soil. The District’s focus is on removing fire-related contaminant-impacted soil so students, staff, and families can safely use campus spaces again.
Why is lead a particular concern for children?
Children can be exposed to lead by swallowing, having dermal (skin) contact, or breathing in lead-contaminated soil. Lead exposure is especially concerning for children under six years of age, since very young children tend to put their hands in their mouths, some young children eat soil and lead has a greater effect on developing brains and nervous systems. California’s Office of Environmental Health Hazard Assessment also notes that lead in soil and dust screening levels are used to help identify areas needing further evaluation or cleanup. DTSC Lead in Soil Fact Sheet
PUSD’s responsibility is to protect students from avoidable exposure to contaminated soil on school campuses. That is why the District closed impacted outdoor areas and is removing and replacing fire-related contaminant impacted soil.
Which campuses and sites are affected?
The current soil removal and restoration work involves 11 District campuses and sites:
Blair High School
Cleveland Elementary School, former site
Field Elementary
Franklin Elementary site
Jefferson Dual Language Children’s Center
John Muir High School Early College Magnet
Longfellow Elementary Magnet
Octavia E. Butler Magnet
PUSD Education Center
San Rafael Elementary
Washington Elementary STEM Magnet School
Four additional fire-burned campuses are pending future review: Eliot, Edison, Noyes, and Loma Alta.
Who is overseeing the cleanup?
The California Department of Toxic Substances Control (DTSC) provides regulatory oversight for this work and will review final soil removal completion reports. PUSD and DTSC are aligned in their commitment to oversee safe soil cleanup and restoration of PUSD campuses following the Eaton Fire.
During soil removal, the District’s environmental consultant, Verdantas, is on site conducting testing and monitoring to ensure impacted soil is properly removed and that clean soil brought back to the site meets applicable safety standards.
Is this work optional?
No. PUSD has an obligation to address fire-related contaminant-impacted soil that poses a health and safety risk on school campuses. DTSC affirms that timely action to remove all impacted soil constitutes the most protective and effective approach on the school properties.
DTSC concurred that there is an imminent and substantial threat to school property users. The work is being done because environmental testing identified fire-related contaminant-impacted soil, outdoor areas have been closed since last year, and the District must return students, staff, and families to safe, healthy, fully usable campuses.
Why does this need to happen now?
The impacted soil removal work must be completed while students are off campus. The District is working during the summer break so campuses can reopen fully and safely for the 2026-2027 school year.
Every delay makes it harder to complete the work before students return and extends the time that play areas, fields, gardens, and other outdoor spaces remain closed.
Why are trees being removed?
PUSD does not want to remove a single tree unnecessarily. The District understands and shares the community’s deep concern for campus trees.
Some trees are located within areas where fire-related contaminant-impacted soil must be removed. In those areas, removing the contaminated soil can require removing trees, vegetation, stumps, roots, and other affected infrastructure so the impacted soil can be fully excavated and replaced with clean soil.
PUSD is reviewing impacted areas site by site and tree by tree to preserve as many native and mature trees as can safely remain. Where no feasible alternative allows contaminated soil to be removed safely and on time, tree removal may be necessary.
Is DTSC requiring PUSD to remove trees?
DTSC is providing regulatory oversight of the soil cleanup and restoration process. PUSD and DTSC are aligned that the fire-related contaminant impacted soil must be addressed to protect students, staff, and the community.
DTSC affirms that timely action to remove all impacted soil constitutes the most protective and effective approach on the school properties. The decision to remove specific trees is based on whether they are located in contaminated soil removal areas and whether there is a feasible way in a timely manner to remove the impacted soil while preserving the tree. PUSD has worked extensively with environmental consultants, arborists, and DTSC to evaluate soil removal approaches. Where trees can safely remain, PUSD is working to preserve them. Where they cannot, the District must complete the soil removal necessary to protect students and reopen campuses safely.
Is PUSD trying to save trees?
Yes. PUSD is attempting to preserve as many native and mature trees as can safely remain.
The District is attempting to preserve native or mature trees located in contaminated soil areas that meet the following specifications:
A trunk more than 18 inches in diameter at a height of 4½ feet, referred to as diameter-at-breast-height, or DBH, above natural grade that is one of the following species: Coast live oak, Engelmann oak, Canyon oak, California sycamore, California walnut, Scrub oak, Valley oak, California bay, Cottonwood, California alder, Black cottonwood, Arroyo willow, and California buckeye.
For other tree species not listed above, the District is attempting to preserve trees with a DBH of 19 inches or greater.
Why are trees being removed if they are not in areas where students usually play?
DTSC affirms that timely action to remove all impacted soil constitutes the most protective and effective approach on the school properties. The decision is based on whether the tree is located in a contaminated soil removal area, not whether students typically play directly under or around that specific tree.
Contaminated soil and dust can move through wind, rain, foot traffic, maintenance activity, and other normal campus uses. PUSD’s responsibility is to restore campuses as safe, fully usable school environments, not to leave contaminated hazardous areas in place because they are less frequently used.
Were protected trees removed at John Muir Early College Magnet on July 1?
No protected trees were removed on July 1 at John Muir Early College Magnet.
The District is abiding by the Board of Education’s authorization to preserve as many native and/or mature trees as possible through alternative methods. Trees cut at John Muir that week did not meet the criteria described above, and included a Sweetgum with a DBH less than 19 inches, three smaller Coast Live Oaks with DBHs of 6 inches, and other non-native or non-mature trees with DBHs of 6 inches or less.
Were native and/or mature trees removed at Jefferson Elementary School?
What is air knifing, and why didn’t it work at Longfellow Magnet School?
Air knifing uses compressed air and vacuum excavation to carefully remove soil from around tree roots while minimizing damage to the roots themselves.
PUSD used this technique around all six protected trees located in the front lawn, to a depth of approximately six inches and, in some locations, as much as one foot. Testing of the exposed soil continued to show elevated levels of lead.
Because air knifing is designed to remove soil selectively around roots and minimize disturbance, it does not necessarily leave the kind of obvious excavation footprint people may expect to see afterward. The area can still appear relatively undisturbed at the surface even though subsurface soil around the critical root zone has been carefully exposed and evaluated.
The District’s arborist concluded that going deeper and removing additional contaminated soil would compromise major structural roots, creating a high likelihood that these very large trees would become unstable or fail. DTSC reviewed this report, and determined that standard excavation methods requiring tree removal would be necessary to remove the contaminated soil.
So while air knifing allowed PUSD to investigate whether the trees could be preserved, it did not provide a safe way to remove enough soil to complete the remediation as outlined in our DTSC-approved Removal Action Workplan.
What happened at San Rafael Elementary School?
San Rafael Elementary School has more than 20 times the California Department of Toxic Substances Control (DTSC) removal limit for arsenic concentrations in some areas of its campus. After reviewing laboratory test results, DTSC stated that there is an “imminent and substantial threat to school property users” and that “timely action to remove all impacted soil constitutes the most protective and effective approach on the school properties.” San Rafael is one of the sites with a site-specific Removal Action Workplan, and the ongoing soil removal work there is part of the District’s broader effort to remove fire-related contaminant-impacted soil and restore safe campus use. The District is doing everything it can under DTSC oversight to assure that the students can return this coming school year to a healthy and safe campus.
The fire-related contaminant impacted soil is in the roots of one tree the City has deemed protected and cannot be injured in any manner. PUSD is attempting to identify solutions that will allow contaminated soil removal from this tree within time to allow a full opening of the campus. Should the tree need to be removed because it is the only method to get the contaminated soil out, PUSD will follow its protocol that uses qualified professionals, including arborists and wildlife biologists, to evaluate applicable tree criteria and nesting bird activity. This will be done to make sure there are no nesting migratory birds. The District remains committed to preserving as many native and mature trees as can safely remain while completing the soil removal necessary to protect students and staff.
How is PUSD protecting migratory nesting birds?
The District has engaged wildlife biologists who conduct observations of trees within contaminated soil areas to ensure that no migratory birds are nesting in those trees.
Observations are conducted within 72 hours before tree removal to ensure migratory nesting birds are not affected. If active nesting is identified, the District will follow applicable requirements before work proceeds. The arborists, tree removal contractor, and wildlife biologist will observe trees for nesting activity while working on the contaminated soil removal project.
What safety measures are in place during soil removal?
All work is being conducted with safety protocols in place, including secured work areas, dust control, particulate monitoring, and appropriate procedures for removal and transport of impacted soil.
The District’s environmental consultant is on site during soil removal to conduct testing and monitoring. Work areas are restricted for safety, and unauthorized access to active remediation zones is not allowed.
What happens after contaminated soil is removed?
Contaminated soil will be removed and replaced with clean soil that is tested and then approved by the DTSC. PUSD is also committed to restoring affected campus landscapes, including planting replacement trees at a minimum 1-to-1-ratio.
The District’s goal is not simply to remove soil. The goal is to return students, staff, families, and community members to safe, healthy, welcoming outdoor spaces where students can learn, play, gather, and thrive.
Will trees be replaced?
Yes. For every tree removed, PUSD is committed to replanting and restoring the shade, beauty, and gathering spaces our school communities depend on.
The District is working with qualified professionals to ensure restoration is thoughtful, appropriate for the campus environment, and consistent with applicable safety, building, fire, and landscape requirements. Replacement trees will generally range from 24-inch box to 48-inch box trees, depending on species availability, campus conditions, irrigation, safety requirements, and long-term maintenance needs.
Restoration will be guided by the PUSD 2026 Landscape and Exterior Space Guidelines and Standard Plant and Tree Palette, which emphasize appropriate shade trees, low-maintenance and drought-tolerant planting, similar watering needs, and campus-specific spacing and clearance requirements.
Will wood from removed trees be preserved or repurposed?
Why not use another method to remediate the soil without removing trees?
PUSD has evaluated soil removal approaches site by site and tree by tree. In some locations, preserving trees may be possible using air knife or air spade technology. The District is currently evaluating this option in consultation with a certified arborist and environmental professionals.
In other locations, alternatives to removal may not allow the District to fully remove the impacted soil safely, effectively, or within the limited timeframe before students return. Other methods, such as bioremediation (biochar, compost, zeolite, etc.), may help manage soil conditions but do not remove the contaminants from the soil. These alternatives may also require long-term controls, monitoring, restrictions, and maintenance that are not appropriate for active school campuses.
Where no feasible alternative allows contaminated soil to be removed safely and on time, tree removal may be necessary.
How has PUSD communicated its soil removal plans?
PUSD has communicated through multiple channels about the soil removal and restoration work. The District created a dedicated Restoring Our Schools webpage with maps, FAQs, and site-specific timelines, held a media briefing, and has sent direct messages to the school community and community partners as this important work has progressed.
DTSC has also engaged directly with the community, including holding a town hall meeting on the project. Video of DTSC April 16, 2026 Public Meeting Draft Removal Action Workplan
For more information, please visit: pusd.us/restoringourschools.
Where can families and community members find more information?
PUSD will continue sharing updates as this work progresses. Resources, site-specific information, timelines, and updates are available at:
PUSD Eaton Fire Soil Removal & Restoration pusd.us/restoringourschools
DTSC
Information about DTSC’s Schools Cleanup Program is available at:
https://dtsc.ca.gov/evaluating-cleaning-up-school-sites/
DTSC reports can also be found through EnviroStor by searching the school name.
https://www.envirostor.dtsc.ca.gov/public/ (search school name).
Other Resources
DTSC Arsenic in Soil: What You Need to Know
DTSC Lead in Soil Fact Sheet
Soil Removal - August 2025
Environmental testing identified areas at nineteen campuses where fire-impacted soil contaminant levels exceed state screening thresholds.
Eight campuses were cleaned up prior to the start of the 2025-2026 school year. PUSD is working under the guidance of the California Department of Toxic Substances Control (DTSC) to address the remaining fire-impacted soil.
School Sites
Soil Removal In Progress
- Altadena Arts Magnet
- Allendale
- Blair
- Cleveland Campus: Aveson and Alma Fuerte Charter
- Field
- Franklin
- Jefferson
- Longfellow
- Madison
- Marshall
- Muir
- Octavia E. Butler
- San Rafael
- Washington
- Webster
Altadena Arts Magnet
Allendale
Blair
Cleveland Campus: Aveson and Alma Fuerte Charter
Field
Franklin
Jefferson
Longfellow
Madison
Marshall
Muir
Octavia E. Butler
San Rafael
Washington
Webster
Non-School Sites
Soil Test Results - May 2025
Soil Test Results – May 2025
PUSD is pleased to report that several schools have been fully cleared, with no elevated levels of harmful fire-related substances detected in soil samples. The full list of schools can be found below.
PUSD is pleased to report that several schools have been fully cleared, with no elevated levels of harmful fire-related substances detected in soil samples. As a result, outdoor playfields and bare dirt areas at those campuses will fully reopen. Normal operations – including recess, PE classes, and athletic team practices – will resume immediately at these locations.
However, in the spirit of full transparency, some school sites did show elevated levels of certain substances in specific outdoor areas. The district is taking immediate, proactive steps to address them.
See the state's fact sheet about lead screening levels
Key actions underway include:
- Continued restriction of access to affected outdoor areas until remediation is complete.
- Ongoing collaboration with local and state health and environmental agencies, including the Los Angeles County Department of Public Health and the Pasadena Public Health Department, to review test results and, if necessary, develop safe, science-based remediation plans that will protect our students and employees.
- Conduct additional soil testing and remediation where needed to maintain and ensure safety.
- Individual school notifications will include summaries, maps of affected areas, and timelines for resolution.
- While the results for heavy metals like lead are in, other results may take longer. Maps will be updated as new data becomes available.
- Updates will be posted here as soon as they are ready.
Messages
Frequently Asked Questions
- Why is it taking longer to get PUSD’s soil test results?
- Why did the district conduct testing?
- What did PUSD test for?
- Who conducted the tests and analyzed the results?
- What were the results?
- What happens if elevated levels are found?
- Were students and staff exposed?
- How will families and staff be notified if elevated levels are found at their school?
- What if no elevated levels were found?
- Why are some results available, while others are not?
- If elevated levels were detected, will instruction be impacted?
- Where can I get more information or updates?
Why is it taking longer to get PUSD’s soil test results?
When Los Angeles County’s soil testing showed elevated levels of lead in areas near the burn zone, PUSD moved forward with conducting its own soil testing. While lead was a principal concern, PUSD consulted with local and state health and environmental agencies and conducted testing of other heavy metals, PAHs, dioxins/furans, and asbestos. This comprehensive approach took additional time, but it reflected our commitment to ensuring a clear, complete understanding of potentially fire-affected site conditions before reopening outdoor areas.
Why did the district conduct testing?
PUSD conducted soil testing in response to findings released in April by the Los Angeles County Department of Public Health (LADPH) regarding elevated lead levels in soil samples collected near the Eaton Fire burn area and after consultation with local and state health and environmental agencies, including the Los Angeles County Department of Public Health and the Pasadena Public Health Department. Working with these experts is part of the district’s ongoing commitment to the safety of students and employees.
What did PUSD test for?
PUSD’s sampling strategies and locations followed best practices and the protocol used in the residential parcel sampling conducted by Los Angeles County Public Health, including surface (0–1 inch) sampling of bare soil areas such as gardens, fields, and play spaces.
Each sample was tested for the following:
- Heavy Metals, including Lead, Arsenic, Cadmium, Chromium , Copper, Nickel, and Zinc.
- Asbestos fibers.
A subset of samples based on location and sensitive areas, approximately 25% per campus, were selected for analysis of the following:
- Polycyclic Aromatic Hydrocarbons (PAHs)
- Dioxins and Furans
Who conducted the tests and analyzed the results?
Verdantas, a state-licensed environmental consulting firm, conducted soil sampling and analysis, following state and federal environmental and public health guidelines. Additionally, certified National Environmental Laboratory Accreditation Program (NELAP) laboratories completed all soil analytical services.
What were the results?
- At a number of school campuses, no elevated levels of fire-related substances were detected, and no further action is needed.
- At other locations, elevated levels of certain fire-related substances were detected. These areas will be addressed through ongoing investigation, and if necessary, targeted remediation of impacted soil will be performed.
- While the results for heavy metals like lead are in, other results may take longer. Maps will be updated as new data becomes available. Updates will be posted at pusd.us/firerelief-safety as soon as they are ready.
What happens if elevated levels are found?
Were students and staff exposed?
How will families and staff be notified if elevated levels are found at their school?
If elevated levels were found:
- Families and staff at that specific campus will receive direct notification from the district.
- Soil test results are available on the PUSD website at pusd.us/firerelief-safety.
What if no elevated levels were found?
Why are some results available, while others are not?
Schools were sampled in a systematic order, and testing is ongoing. The results are still being received from state-certified laboratories, and maps and full reports will be posted at pusd.us/firerelief-safety as they become available.
If elevated levels were detected, will instruction be impacted?
Where can I get more information or updates?
Visit the district website at pusd.us/firerelief-safety. Testing updates and results will be posted.
Anyone who is concerned about exposure to lead from wildfire can obtain blood lead testing for themselves, and their children, in one of three ways:
Visit Your Medical Provider
- Ask your doctor for a blood lead test.
- Testing is covered by most insurance plans, including Medi-Cal.
Go to a Quest Lab for a Free Blood Lead Test
- Dial 1-800-LA-4-LEAD to request a free appointment through Quest Labs.
- Simple, convenient, and confidential.
In-Person Mobile Blood Lead Testing
- For a limited time, Los Angeles County Department of Public Health will offer FREE mobile blood lead testing. Upcoming events are listed below. Additional events will be added in the months to come. More information can be found at the Fire Safety and Health information website.
See previous FAQ:
At Pasadena Unified School District (PUSD), the safety of our students and staff is our highest priority. Following the Eaton Fire and related soil health concerns identified by the Los Angeles County Department of Public Health, PUSD has completed a comprehensive round of soil testing at all school sites in partnership with a certified environmental consulting firm.
Several schools have been cleared and deemed safe for normal outdoor use, while others will undergo targeted remediation to ensure all outdoor areas meet health and safety standards.
We are committed to full transparency and swift action. Please explore the sections below for school-specific updates, safety measures, and answers to frequently asked questions.
Community Message
News Release
Soil Test Results
PUSD is pleased to report that several schools have been fully cleared, with no elevated levels of harmful fire-related substances detected in soil samples. The full list of schools can be found below.
PUSD is pleased to report that several schools have been fully cleared, with no elevated levels of harmful fire-related substances detected in soil samples. As a result, outdoor playfields and bare dirt areas at those campuses will fully reopen. Normal operations – including recess, PE classes, and athletic team practices – will resume immediately at these locations.
However, in the spirit of full transparency, some school sites did show elevated levels of certain substances in specific outdoor areas. The district is taking immediate, proactive steps to address them.
See the state's factsheet about lead screening levels
Key actions underway include:
- Continued restriction of access to affected outdoor areas until remediation is complete.
- Ongoing collaboration with local and state health and environmental agencies, including the Los Angeles County Department of Public Health and the Pasadena Public Health Department, to review test results and, if necessary, develop safe, science-based remediation plans that will protect our students and employees.
- Conduct additional soil testing and remediation where needed to maintain and ensure safety.
- Individual school notifications will include summaries, maps of affected areas, and timelines for resolution.
- While the results for heavy metals like lead are in, other results may take longer. Maps will be updated as new data becomes available.
- Updates will be posted here as soon as they are ready.
- Allendale ES
- Altadena ES
- Blair MS & HS
- Don Benito Fundamental School
- Field ES
- Hamilton ES
- Jackson STEM
- Jefferson CC
- John Muir HS
- Longfellow ES
- Madison ES
- Marshall Secondary
- McKinley School
- Norma Coombs ES
- Octavia E. Butler Magnet
- Pasadena HS
- San Rafael ES
- Sierra Madre ES
- Sierra Madre MS
- Washington ES
- Washington Children's Center
- Webster ES
- Willard ES
- Wilson Campus: Aveson, CIS, PALs, Rose City HS, Twilight and Willard Children's Center
- Education Center
- District Service Center
- Audubon Campus: Odyssey Charter
- Burbank campus: Stratford (private)
- Cleveland Campus: Aveson and Alma Fuerte Charter
- Hodges
- La Casita
- Linda Vista Campus